How Percent Spent Invoice Amounts Are Calculated

Project Billing uses the percent spent invoice method to recognize revenue as progress is calculated.

The Generate Invoice process:

  1. Calculates the percent spent amounts

  2. Creates events

Prerequisites and Settings That Affect Percent Spent Invoice Amounts

The following prerequisites and settings impact the percent spent invoice for a contract line:

  • A current baseline cost (or cost and revenue) budget version must exist for all projects associated with the contract line, if the class of the cost plan type of the percent spent invoice billing extension is budget.

  • An approved cost (or cost and revenue) forecast version must exist for all projects associated with the contract line, if the class of the cost plan type of the percent spent invoice billing extension is forecast.

  • All existing actual costs for projects associated with the contract line must first be summarized.

  • The Bill-Through Date parameter of the Generate Invoice process is a date that's on or after the last day of the current accounting period.

  • The contract line amount or the funded amount for each project and task associated with the contract line must be greater than zero.

  • The contract line must be assigned to a bill plan that uses the percent spent invoice method.

  • The bill plan contains a calculation level that creates events for the contract line or associated project.

The following table describes the effects of the calculation level selection.

Calculation Level

Description

Contract line

The percent spent invoice method creates separate events for each project and task associated with the contract line. Each event contains the project and task associated with the contract line.

Associated project

The percent spent invoice method creates one event for the contract line. The event contains the total of all percent spent amounts for all projects and tasks associated with the contract line. The event doesn't contain a project or task.

How Associated Projects Actual Cost is Calculated

The associated projects actual cost is the inception-to-date (ITD) actual cost. Inception-to-date actual cost is derived by summing the actual costs summarized by accounting period up to and including the maximum accounting period with a period end date that's on or before the To Date of the Generate Invoice process. To include current period costs in the calculation, use a To Date that's on or after the last day of the current accounting period.

How Percent Spent Invoice Amounts are Calculated

The following examples show how percent spent invoice amounts are calculated for the contract line and associated project.

Contract Line Percent Spent Example

The following formula calculates the percent spent invoice amount for the contract line.
Event Amount equals left parenthesis, left parenthesis, left parenthesis, left parenthesis Sum of ITD Actual Cost for every task associated to the contract line, right parenthesis, divided by left parenthesis Sum of Total Budgeted Cost for every task associated to the contract line, right parenthesis, right parenthesis, multiplied by Contract Line Amount, right parenthesis, minus Sum of Existing Invoice Event Amounts for the Contract Line, right parenthesis.

Task

ITD Actual Cost

Total Budgeted Cost

Contract Line Amount

Sum of Existing Invoice Events

Percent Spent Event Amount

1

60

300

2

40

100

Line 1

100

400

1000

100

150

Associated Project Percent Spent Example

The following formula calculates the percent spent invoice amount for the associated project.
Event Amount equals left parenthesis, left parenthesis, left parenthesis, left parenthesis Sum of ITD Actual Cost for every subtask that's part of the associated task, right parenthesis, divided by left parenthesis Sum of Total Budgeted Cost for every task that's part of the associated task, right parenthesis, right parenthesis, multiplied by Associated Project Funded Amount, right parenthesis, minus Sum of Existing Invoice Event Amounts for the Associated Project, right parenthesis.

Task

ITD Actual Cost

Total Budgeted Cost

Associated Project Funded Amount

Sum of Existing Invoice Events

Percent Spent Event Amount

1.1

40

100

1.2

20

200

1

60

300

600

75

45

2.1

30

60

2.2

10

40

2

40

100

400

25

135