Import Collaboration Order Forecasts

Use this process to import external collaboration order forecasts from file-based data import (FBDI) files into Oracle Fusion Cloud Supply Chain Collaboration interface tables when you use the Load Interface File for Import scheduled process.

When to Use

The Import Collaboration Order Forecasts scheduled process is the import process that loads collaboration order forecasts from FBDI files when you use the Load Interface File for Import scheduled process. When using the Import Collaboration Order Forecasts scheduled process, first select the Load Interface File for Import scheduled process, and then select the previously loaded data file that was uploaded using the scm/collaborationOrderForecast/import account from the File Import and Export page.

For more information on the FBDI mechanism, see File-Based Data Import (FBDI) for SCM.

Privileges Required

  • Import Collaboration Order Forecasts (VCS_COLLABORDERFORECAST_IMPORT_PRIV)

Specifications

Review these specifications before setting up this scheduled process:

Specification Description
Job Type Submitted as an ad hoc job, if required.
Frequency As required by your business, usually after your planning cycle ends.
Time of Day After work hours is recommended but can be submitted any time based on your requirements.
Duration Runtime for the process varies and depends on the number of forecast records that must be processed.
Compatibility There are no compatibility issues with other scheduled processes.

Parameters

There aren't any parameters for this scheduled process.

Troubleshooting Information

  • You can view the status of the process in the Scheduled Processes work area. A succeeded status indicates that the process has completed successfully.
  • Validation errors and warning messages that prevented this scheduled process from completing successfully display in the error log.
    Note: Collaboration relationships and a collaboration plan must already exist to load the data into the interface tables successfully.
  • The process does not perform interactive warning validations.
  • After you submit the scheduled process, you can't perform any of these tasks in the Scheduled Processes work area:
    • Resubmit it
    • Put it on hold
    • Cancel the process
    • Release the process