Set Pick-pack Lead Time

You need to set the pick-pack lead time for the order line in the Oracle Plan Inputs task in the Oracle Plan Inputs work area.

  1. In the Oracle Plan Inputs work area, select the Maintain Supply Network Model task.
  2. Set the pick-pack lead time at organization level.

    Navigate to the Organization tab and set the pick-pack lead time for the selected organization.

  3. Set the pick-pack lead time at carrier level.

    Navigate to the Carrier tab and set the pick-pack lead time for the selected carrier.

  4. Set the pick-pack lead time at interlocation shipping networks level.

    Navigate to the Interlocation Shipping Networks tab and set pick and pack lead time for the selected source, destination, and carrier combination.

  5. Click Save.
    You can also define pick-pack lead time using FBDI file upload framework. In this case, the existing value of pick-pack lead time is overwritten by the new value set in the FBDI file.