Migration Sequence

Here’s the order in which you must perform the migration tasks.

  1. Export Agile PLM data.
  2. Import items, revisions, manufacturer parts, AML, and attachments. This is also a prerequisite for importing change orders.
  3. Import structures, reference designators, and substitute components.
  4. Import change orders.