Transfer Costs to Cost Management

Use the Transfer Costs to Cost Management scheduled process to transfer Accounts Payable invoice information to Oracle Cost Management.

Accounts Payable invoice information is input into Receipt Accounting for reconciling receipt accrual amounts, determining uninvoiced receipt quantity, reconcile estimated landed cost amounts with actuals, and to adjust the cost of receipts. Accounts Payable invoice information is also input into Cost Accounting for inventory value adjustments. After Accounts Payable invoices are accounted, the information is considered stable and ready for transfer to Cost Management.

When to Use

The Transfer Costs to Costing scheduled process should be scheduled to run at least once per day to ensure receipt accounting and cost accounting are up to date with timely receipt information. This process can also be run more often than once per day depending on business needs such as prior to decision points, at end of day, or or after peak invoice processing activities are completed

You can coordinate the schedule of this process to run in parallel with the Transfer Transaction from Receiving to Costing process and the Transfer Transactions from Inventory to Costing process. You should run this in coordination with the frequency and timing of the downstream scheduled processes Create Receipt Accounting Distributions and Create Cost Accounting Distributions, and also in coordination with the scheduled processes Create Uninvoiced Receipt Accruals, Match Receipt Accruals, and Manage Landed Costs. You should schedule this process such that it is completed just prior to running the coordinated downstream processes. You can use process sets to coordinate this scheduled process with parallel and downstream processes.

Privileges Required

  • Transfer Costs to Cost Management (AP_TRANSFER_COSTS_TO_COST_MGMT)

Specifications

Review the following before setting up this process:
Specification Description
Job Type Scheduled or as needed.
Frequency Daily or more than once per day.
Time of Day Any time.
Duration Runtime of this process will vary based on the number of transactions.
Compatibility There are no incompatibilities. This process is a prerequisite process and should be coordinated with the other scheduled processes that rely on this process to complete.

Parameters

Parameter Optional or Required Description Parameter Value Special Combinations Required Notes
Business Unit Required You can run this process for a specific business unit. Business Unit name N/A N/A
Cutoff Date Required You can use the cutoff date to control and limit the amount of data to be transferred in situations where there is catchup, such as new implementation or business restructure. Otherwise, this can be set to the current date, the last day of the current accounting period, or a future date. Date N/A N/A

Troubleshooting Information

Ensure the Accounts Payable invoice has been successfully posted to General Ledger. Invoices are considered stable information after they have been posted to General Ledger. Invoices not posted to General Ledger aren't transferred to Cost Management.