Example of Project-Specific Safety Stock Planning with Days of Cover

You can use days of cover calculations while determining the safety stock used in planning for unexpected changes in project demands. Let's use an example to understand how days of cover are calculated.

Scenario

How Days of Cover Are Calculated

Let's say you're working on a project-based plan with these netting rule specifications:

  • Reservation level is Project Group

  • Netting sequence order:

    1. Net project task supply

    2. Net excess project supple

    3. Net common supply

Sequence Number Demand Attribute Demand Operator Supply Attribute Supply Operator
1 Project Group Any Project Group Matches Demand Value
Project Any Project Matches Demand Value
Task Any Task Matches Demand Value
2 Project Group Any Project Group Matches Demand Value
Project Any Project Matches Demand Value
Task Any Task Any
3 Project Group Any Project Group Matches Demand Value
Project Any Project Any
Task Any Task Any
4 Project Group Any Project Group Blank
Project Any Project Blank
Task Any Task Blank

Let's also assume these are your item attributes:

  • Safety stock planning method is Days of Cover

  • Days of Cover Demand period is 5 days

  • Days of Cover period is 2 days

This table lists out the daily number of demand units for each task.

Project

Task

Day 1 (Common Demand = 30 units)

Day 2 (Common Demand = 30 units)

Day 3 (Common Demand = 30 units)

Day 4 (Common Demand = 30 units)

Day 5 (Common Demand = 30 units)

Day 6 (Common Demand = 30 units)

Day 7 (Common Demand = 30 units)

P1

T1

10

-

20

20

-

20

20

P1

T2

10

10

25

25

-

25

25

P2

T1

-

-

-

10

10

-

10

Here's how the total demand, average daily demand and safety stock days of cover duration are calculated:

  • The total demand is the sum of the common demand and the demand for each project and task combination. For Day 1, the total demand is 30+10+10=50 units.

  • The average daily demand is the sum of total daily demands from the day in question divided by the days of cover demand period. For Day 1, it's (50+40+75+85+85)/5 = 67 units.

  • The safety stock days of cover is the product of the average daily demand and the days of cover. For Day 1, it's 67*2 = 134 days.

Day

Day 1

Day 2

Day 3

Day 4

Day 5

Day 6

Day 7

Total Demand

50

40

75

85

85

85

85

Average Daily Demand

67

74

83

68

51

34

17

Days of Cover

2

2

2

2

2

2

2

Safety Stock Days of Cover

134

148

166

136

102

68

34

How Plans Maintain the Safety Stock Calculated Using Days of Cover

Let's now use the safety stock days of cover calculation to understand how supply plans maintain the safety stock by assessing available on-hand supply and safety stock to determine a projected available balance. When the number of projected available balance units is less than the number of safety stock units, the creation of more supply units is recommended to make up the difference.

  • The project-based plan calculates days of cover safety stock levels at common for common and project demands.

  • Common on-hand units are used to net common demands and project demands based on the attribute-based netting sequence steps.

  • Common on-hand units also satisfy the common safety stock levels throughout the planning horizon.

Project

Task

Day 1 (Common Demand = 30 units)

Day 2 (Common Demand = 30 units)

Day 3 (Common Demand = 30 units)

Day 4 (Common Demand = 30 units)

Day 5 (Common Demand = 30 units)

Day 6 (Common Demand = 30 units)

Day 7 (Common Demand = 30 units)

P1

T1

10

-

20

20

20

20

20

P1

T2

10

10

25

25

25

25

25

P2

T1

-

-

-

10

10

10

10

Demand Type

Day 1

Day 2

Day 3

Day 4

Day 5

Day 6

Day 7

Safety Stock

134

148

166

136

102

68

34

On-Hand Common Supply

250 (Common demand on each day plus the demand for all project and tasks on Day 6)

-

-

-

-

-

-

Available On-Hand Common Supply

220

190

160

130

100

30

0

Projected Common Available Balance

220

190

166

136

106

68

38

On-Hand Supply for PG1-P1-T1

100

-

-

-

-

-

-

PO Supply for PG1-P1-T2

85

-

-

-

-

-

-

Planned Order Supply for PG1-P1-T1

-

-

-

-

-

-

55

Planned Order Supply

-

-

6

-

-

32

-

The common on-hand 250 units satisfies the common demand from Day 1 to Day 7. Additionally, the plan maintains sufficient supply to satisfy common safety stock levels calculated based on days of cover. On Day 3, a common supply of 6 units is recommended by the plan to maintain sufficient stock for the common safety stock level calculated using days of cover. On Day 6, the plan nets 40 units of the common on-hand units to project demands based on project- netting sequences. On Day 6, because the common stock isn't sufficient to maintain safety stock level, the plan recommends 32 units of common supply. On Day 7, the planned order supply of 55 units with the project and task is recommended by the plan based on the attributes selected for Demand Grouping in Attributes for Planned Orders of the attribute-based netting rules.