Production Campaign Views

You can review campaigns in the campaigns table and Gantt chart.

Campaigns Table

The table beneath the Gantt chart displays detailed campaign information. Select a Resource to view its campaigns. Select Open or Completed to view campaigns with that status.

To access campaign actions, scroll to the right and open the Actions menu in the last column for the campaign. You can:
  • Select Edit to update campaign details.
  • Select Details to manage work order assignments and sequencing.
  • Select Complete to complete the campaign.
  • Select Delete to delete the campaign.

Gantt Chart

The Gantt chart displays campaigns as task bars. Calendar downtime appears as a gray background, and changeovers appear as narrower black task bars. Tooltips provide information about campaigns and changeovers between campaigns.

For a campaign with assigned work orders and a remaining unassigned quantity, the task bar has two portions:
  • Assigned portion: Extends through the end date of the last assigned work order and appears in the campaign’s color.
  • Unassigned portion: Represents the remaining unassigned amount and appears in a lighter shade.

The Gantt chart displays data only after you calculate the campaign plan at least once.