How Campaign Plans Are Calculated

The campaign plan calculation determines campaign start and end dates using the campaign sequence and the work order sequence within each campaign.

To run the calculation, select Calculate at the top of the page.

Resource Availability and Changeovers

The calculation considers campaign resource availability and calendar downtime. It applies the attribute-based changeover rules you defined for:
  • Major changeovers between campaigns.
  • Minor changeovers between work orders within a campaign.

These factors can extend the elapsed duration of a campaign.

Assigned and Unassigned Portions

For assigned work orders, the calculation uses the resource usage hours defined on the work order operation resources.

For the unassigned portion, it uses the campaign’s production rate to calculate the required resource usage hours. The unassigned quantity is the campaign quantity minus the total quantity of assigned work orders.

Resource Assignments

The calculation uses the resource assigned to each campaign. It doesn’t move campaigns to other resources or make offloading decisions.