How Campaign Plans Are Calculated
The campaign plan calculation determines campaign start and end dates using the campaign sequence and the work order sequence within each campaign.
To run the calculation, select Calculate at the top of the page.
Resource Availability and Changeovers
- Major changeovers between campaigns.
- Minor changeovers between work orders within a campaign.
These factors can extend the elapsed duration of a campaign.
Assigned and Unassigned Portions
For assigned work orders, the calculation uses the resource usage hours defined on the work order operation resources.
For the unassigned portion, it uses the campaign’s production rate to calculate the required resource usage hours. The unassigned quantity is the campaign quantity minus the total quantity of assigned work orders.
Resource Assignments
The calculation uses the resource assigned to each campaign. It doesn’t move campaigns to other resources or make offloading decisions.