Resequence Campaigns and Work Orders
You can change the order of campaigns on a campaign resource and the order of work orders within each campaign.
Resequence Campaigns
- In the campaigns table, scroll to the right and open the Actions menu in the last column for the campaign.
- Select Edit.
- In the drawer, change the Campaign Sequence number.
- Select Update.
Select Calculate at the top of the page to update campaign start and end dates based on the revised sequence.
Resequence Work Orders
- In the campaigns table, scroll to the right and open the Actions menu in the last column for the campaign.
- Select Details.
- In the drawer, select Assigned.
- Select the work order you want to move, then use the up or down arrow to change its sequence. Alternatively, edit the Work Order Sequence field directly.
- Select Apply above the table.
You can’t move a work order past a work order with a status of Closed, Canceled, or Completed.