5.4.1 Inspecting the Machine After it is in Place

This procedure describes how to visually examine the Oracle Exadata Rack physical system after it is in place, but before power is supplied.

  1. Check the rack for damage.

  2. Check the rack for loose or missing screws.

  3. Check Oracle Exadata Rack for the ordered configuration. Refer to the Customer Information Sheet (CIS) on the side of the packaging.

  4. Check that all cable connections are secure and firmly in place as follows:

    1. Check the power cables. Ensure that the correct connectors have been supplied for the data center facility power source.

    2. Check the network data cables.

  5. Check the site location tile arrangement for cable access and airflow.

  6. Check the data center airflow that leads in to the front of Oracle Exadata Rack.