3.5.1 Procedure 11 Switch Configuration

Table 3-15 Procedure 11 Switch Configuration

STEP # This procedure Configures the Switches of a newly installed ELAP Server Pair. Check off (√ )each step as it is completed. Boxes have been provided for this purpose under each step number. IF THIS PROCEDURE FAILS, CONTACT ORACLE TECHNICAL SERVICES AND ASK FOR ASSISTANCE.

1. ☐

Make the cross- over cable connections.

NOTE: THIS IS IMPORTANT

CONNECT the LAG cable from Port 1 of Switch1A to Port 1 of Switch1B.

DISCONNECT the LAG cable from Port 2 of Switch1A to Port 2 of Switch1B.


Two Telco switches labeled A and B, with crossover connections marked.

Please note that the switch configuration should only be attempted by a skilled technician.

All uplinks should be removed while switch configuration.

There should not be any loop in the switches during their configuration.

2. ☐

MPS A: Console login.

Login using serial console.

consolelogin: root 
password:  password 

3. ☐

MPS A: Start services for switch configuration

Change the startup information for tftp:

# chkconfig tftp on

Change the startup information for xinetd:

# chkconfig xinetd on

Start xinetd

# service xinetd start

Start and enable tftp service:

#systemctl start tftp

#systemctl enable tftp

Check whether both xinetd and tftp are up and running:

#service status xinetd tftp

4. ☐

MPS A: Verify the bond0 configuration.

Verify that the eth03 is the default primary port of the bond0.

# cat /proc/net/bonding/bond0 | grep "Currently Active Slave" Currently Active Slave: eth03

5. ☐

MPS A: Set the permissions for BiNOS- T5CL3_24G- G_v8.6.R6.2.bin

Change the permissions of BinOS file to 644

# chmod 644

/var/TKLC/switchconfig/BiNOS-T5CL3_24G-G_v8.6.R6.2.bin

Verify the permission of the file

# ls -l /var/TKLC/switchconfig total 4432

-rw-r--r-- 1 root root 4537660 Nov 10 07:26 BiNOS-T5CL3_24GG_v8.6.R6.2.bin

6.

☐

MPS A: Start platcfg utility.

# su - platcfg

7.

☐

MPS A: Navigate to the Network Configuration Menu.

On the platcfg Main Menu, select Network Configuration and press [ENTER].


Main Menu with Network Configuration selected for switch configuration.

8.

☐

MPS A: Navigate to the Configure

Switch Menu.

On the Network Configuration menu, select Configure Switch and press [ENTER].


Network Configuration Menu with Configure Switch selected.

9.

☐

MPS A: Select to configure “switch1B –

Lower Switch in Frame 1” and press Enter.

On the Select Switch Menu, select “switch1B – Lower Switch in Frame 1” and press [ENTER].


Select Switch Menu with switch1B, the lower switch in frame 1, selected.

10.

☐

MPS A: Confirm Switch Configuration.

Select Yes and press [ENTER] to configure Switch 1B.


Confirmation warning that configuring switch1B will disrupt network connectivity.

11.

☐

MPS A: Switch Configuration Screen.

Configuring the switch takes about 10 minutes, once complete press [ENTER] to continue.


Console output reporting successful configuration of switch1B.

12.

☐

MPS A: Switch Configuration completion screen.

The switch configuration completion screen is displayed. Press [ENTER] to continue.


Message reporting that switch configuration completed successfully.

13.

☐

MPS A: Select to configure “switch1A – Upper Switch in Frame 1” and press Enter.


Select Switch Menu with switch1A, the upper switch in frame 1, selected.

On the Select Switch Menu, select “switch1A – Upper Switch in Frame 1” and press [ENTER].

14.

☐

MPS A: Confirm Switch Configuration.

Select Yes and press [ENTER] to configure Switch 1A.


Confirmation warning that configuring switch1A will disrupt network connectivity.

15.

☐

MPS A: Switch Configuration Screen.


Console output reporting successful configuration of switch1A.

Configuring the switch takes about 10 minutes, once complete press [ENTER] to continue.

16.

☐

MPS A: Switch Configuration completion screen.


Message reporting that switch configuration completed successfully.

The switch configuration completion screen is displayed. Press [ENTER] to continue.

17.

☐

MPS A: Exit out of platcfg.

Select Exit and press [ENTER] to return to the Network Configuration Menu. Select Exit and press [ENTER] to return to the Main Menu.

Select Exit and press [ENTER] to exit out of platcfg.

18.

☐

MPS A: Connect the cross-over cable from Port 2 of Switch1A to Port 2 of Switch1B at this time.

Make sure that the LAG cable is connected from Port 1 of Switch1A to Port 1 of Switch1B.

CONNECT the LAG cable from Port 2 of Switch1A to Port 2 of Switch1B.


Two Telco switches labeled A and B, with the restored crossover connections marked.

19.

☐

MPS A: Stop services after switch configuration.

Change the startup information for tftp:

# chkconfig tftp off

Change the startup information for xinetd:

# chkconfig xinetd off

Stop xinetd

# service xinetd stop

20.

☐

Procedure complete.

This procedure is complete.