Importing Options -- Resources

If resource security is enabled (you have limited or no resource access), the following restrictions apply when importing resources:

A) Limited resource access:

  Keep Existing

Update Existing

 

Insert New Do Not Import

New resource

See Note.

The resource is added as a child under your root resource node.

 

The resource is added as a child under your root resource node. The resource is added as a child under your root resource node.  
Existing resource (under your root node)   The resource data is updated. The resource is added as a child under your root resource node. Resource ID is appended by "-1". (For example, if the Resource ID is "Labor", the new Resource ID will be "Labor-1")    
Existing resource (outside your root node)