Set the project default activity calendar

  1. Choose Enterprise, Projects and display Project Details.
  2. Click the Defaults tab.
  3. In the Defaults for New Activities section, select a default calendar.

Tip:

Click the Options bar in the Select Default Project Calendar dialog box to display global or project calendars.

Note:

The default calendar is only used for new activities. Changing this setting does not affect existing activities.