Set the project default activity percent complete type

  1. Choose Enterprise, Projects and display Project Details.
  2. Click the Defaults tab.
  3. In the Defaults for New Activities section, select the default percent complete type.

    Note:

    The default percent complete type is only used for new activities. Changing this setting does not affect existing activities.