Set the project default activity duration type

  1. Choose Enterprise, Projects and display Project Details.
  2. Click the Defaults tab.
  3. In the Defaults for New Activities section, select the default duration type.

    Note:

    The default duration type is only used for new activities. Changing this setting does not affect existing activities.