Set the project default activity type

  1. Choose Enterprise, Projects and display Project Details.
  2. Click the Defaults tab.
  3. In the Defaults for New Activities section, select the default activity type.

    Note:

    The default duration type is only used for new activities. Changing this setting does not affect existing activities.