Status Updates overview

With the optional P6 Team Member Web module installed, project managers can require that updates made to activities must be approved before they are applied. If they have the appropriate OBS privileges, reviewers can process those updates in P6 Professional when connected to a P6 EPPM database. Users assigned the Project Superuser or Admin Superuser profiles can also process status updates.

Status updates are be configured in P6 and can require one or multiple reviewers to approve each update before applying it. Reviewers can approve, reject, hold, remove hold from, or override a status update and can communicate with the submitting user by email or in a Discussion thread saved with the status update.

Note:

You cannot review status updates for projects that are checked out, projects that are opened exclusively by another user, or if you are working in offline mode.