Actual Total Cost (Activities)
Actual Total Cost field
The actual total cost incurred for the activity as of the project data date.
Calculated as Actual Labor Cost plus Actual Nonlabor Cost plus Actual Material Cost plus Actual Expense Cost.
Actual Total Cost field
The actual total cost incurred for the activity as of the project data date.
Calculated as Actual Labor Cost plus Actual Nonlabor Cost plus Actual Material Cost plus Actual Expense Cost.