Assigning a Base Calendar to a Project Calendar
Assign a base calendar to determine holidays and exceptions for the selected project calendar.
To assign a base calendar:
- On the
Navigation Menu, expand
Administration and click Enterprise Data. - On the Enterprise Data page, expand Projects and click Project Calendars.
- On the Project Calendars page:
- In the Select Base Calendar dialog box, select a calendar and click Select.
- Click Save.