Assigning a Base Calendar to a Resource Calendar

Assign a base calendar to apply all the exception days (for example holidays and other work or nonwork days) from the base calendar for the selected resource calendar.

To assign a base calendar:

  1. On the "" Navigation Menu, expand "" Administration and click Enterprise Data.
  2. On the Enterprise Data page, expand Resources and click Resource Calendars.
  3. In the Resource Calendars pane:
    1. Expand Personal Calendars or Shared Calendars and select a calendar.
    2. Click the Summary tab.
    3. In the Base Calendar field, click "" Select.
  4. In the Select Base Calendar dialog box, select a calendar.
    1. Click Select.