At Completion Labor Units
At Completion Labor Units field
The sum of the actual plus remaining units for all labor resources assigned to the activity or all activities in the project.
It is the same as the planned labor units if the activities in the project are not started, and the actual labor units once the activities are completed.
Calculated as Actual Labor Units plus Remaining Labor Units.