At Completion Total Cost

At Completion Total Cost field

The estimated cost at completion for the activity or all activities in the project.

Calculated as the Actual Total Cost plus the ETC (estimate-to-complete) cost. The method for computing ETC depends on the Earned Value technique selected for the activity's WBS.