At Completion Nonlabor Units

At Completion Nonlabor Units field

The nonlabor units at completion. It is the sum of the actual plus remaining units for all nonlabor resources assigned to an activity or all activities in the project.

It is the same as the planned nonlabor units if the activities are not started, and the actual nonlabor units once the activities are completed.

Calculated as Actual Nonlabor Units plus Remaining Nonlabor Units.