At Completion Nonlabor Cost

At Completion Nonlabor Cost field

The nonlabor cost at completion. It is the sum of the actual plus remaining costs for all nonlabor resources assigned to the activity or all activities in the project.

It is the same as the planned nonlabor costs if the activities are not started, and the actual nonlabor costs once the activities are completed.

Calculated as Actual Nonlabor Cost plus Remaining Nonlabor Cost.