Configuring Activity View Gantt Chart

Configure Gantt chart options to determine how the chart will display.

To configure Gantt chart options:

  1. On the "" Navigation Menu, expand "" Projects and click Activities.
  2. On the Activities page:
    1. Click "" Customize View.
    2. In the Manage View dialog box, click the Gantt tab.
    3. On the Gantt tab:
      • Select the Data date line option to show the data date on the Gantt.
      • Select the Relationship lines option to show lines between activities on the Gantt.
      • Select the Non-driving relationships option to draw lines between activities on the Gantt even where the relationship doesn't affect the successor's dates.
      • Select the Sight Lines option to show vertical lines between each segment of the timescale.
      • Select the Non-work time shading option to have non-work time shaded on the Gantt.
      • Select a Timescale.
    4. Click Apply.

Tip:

  • The Gantt chart only prints if it is displayed.
  • You can right click on the timescale to change the timescale of the Gantt.