Configuring Project Calculations

Configure project calculations to define how the application will compute values concerning activities, earned value, and units and costs.

To configure project calculations:

  1. On the "" Navigation Menu, expand "" Projects and click EPS.
  2. On the EPS page:
    1. Select a project.
    2. Click "" Context and select Set Project Preferences.
    3. In the Project Preferences dialog box, click Calculations.
    4. On the Calculations page:
      • In the Resource Assignments section, specify how the units and costs on assignments and activities should be updated when actual units or costs fields are changed.
      • Select whether to Recalculate actual units and costs when Duration % Complete changes.
      • Select whether to Link actual to date and actual this period units and costs.
    5. Click Apply.