Calendar: Click
Select to assign a calendar to the resource that is different from the default calendar. Click Create Personal Calendar to create a unique calendar for the resource, or select an existing calendar, and click Select.
Calculate Costs from Units: Select this option to indicate that any new assignment for this resource will have its cost recalculated whenever any quantity changes occur, such as changing an activity's remaining duration.
Auto Compute Actuals: Select to automatically calculate the selected resource's actual quantity of work according to the project plan rather than reported hours in the Timesheets tab of P6 Team Member. Clear this option if the user will use timesheets.
Overtime Allowed: Select to enable the labor resource to record overtime hours for activities.
Default Units/Time: Use the default value or change the default units/time value. Enter these values as units per duration or as a percentage, depending on your choice in the Units/Time Format area of the My Preferences page.
Currency: Click
Select to select a currency that is different from the default currency, and click Select.
Overtime Factor: Type the number by which the resource's standard price should be multiplied to determine the resource's overtime price.
Team Member: Configure timesheet settings for the selected resource.