Configuring the Resources Assignments Gantt Chart Bars

Configure the bar settings for the Gantt chart view on the Resources Assignments page. You can set features for up to three bars per assignment.

To configure the resource assignments Gantt chart bars:

  1. On the "" Navigation Menu, expand "" Resources and click Assignments.
  2. On the Assignments page, click "" Customize View.
  3. In the Customize View dialog box:
    1. Click Bars.
    2. On the Bars tab click "" Add ""and select Bar or Label.
    3. Select a bar or label.
    4. If you selected a bar:
      • Click the Bar Type list and choose one of the available bar types.

        Note:

        You can configure multiple bars. Set at least one bar to Current.

      • In the Height field, select the height for the bar.
      • In the Bar Color field, select a color.
      • Select Show Progress to show progress on the bar.
      • If you chose to show progress, select a Progress Color and Progress Style.
    5. If you selected a label:
      • In the Label Field field, select a bar label.
      • In the Height field, select the font size for the label.
      • In the Color field, select a color for the bar label.
      • Click Apply.