Creating Activity Relationships

You can create activity relationships in the Gantt chart to show interdependencies between activities.

To create an activity relationship:

  1. On the "" Navigation Menu, expand "" Projects and click Activities.
  2. On the Activities page:
    1. Click "" Gantt View.
    2. Click "" Gantt Settings and select to show relationships.
    3. Hover either to the left or right of a bar.
    4. Drag the circle to the left or right end of a bar representing the activity you want to link.

      Note:

      Where you drag the relationship on each bar determines the type of relationship.

    5. Click Save.

Tip:

  • You can scroll through the Gantt chart while while dragging a relationship to find a related bar.
  • To delete a relationship, right-click the relationship line and select Delete Relationship.
  • If multiple projects are open, you can create external relationships.
  • You can also create new relationships and view or configure existing predecessor or successor relationships, from the Relationships detail window.