Configuring Activity Relationships

Configure activity relationships to adjust interdependencies between different activities.

To configure activity relationships:

  1. On the "" Navigation Menu, expand "" Projects and click Activities.
  2. On the Activities page:
    1. Click "" Gantt View.
    2. Click "" Gantt Settings and select to show relationships.
    3. Right click the relationship line of the relationship you want to configure and click Edit Relationship.
      • In the Edit Relationship dialog box, configure the type and lag and click Apply.
    4. On the Activities page, click Save.

Tip:

You can also configure predecessor and successor relationships from the Relationships detail windows.