Assigning Predecessor Relationships
You can assign predecessor relationships to the activities in a project.
To assign a predecessor relationship:
- On the
Navigation Menu, expand
Projects and click Activities.
Tip:
- Only Finish to Start relationships are created in the Assign Relationships panel. To create other types of relationships create the relationships in the Gantt View. Alternatively you can create the relationships in the Assign Relationships panel and then change the relationship type manually in the Relationships detail window.
- When selecting a predecessor or successor activity, you can choose from activities in the open projects only.