Creating Resource Calendars

Create a resource calendar to determine when a resource can work.

To create a resource calendar:

  1. On the "" Navigation Menu, expand "" Administration and click Enterprise Data.
  2. On the Enterprise Data page, expand Resources and click Resource Calendars.
  3. On the Resource Calendars page:
    1. Click on Personal Calendars to create a private calendar for the resource, or click on Shared Calendars to create a calendar for multiple resources to share that the resources cannot edit.
    2. Click "" Add.
  4. If you are creating a Personal Calendar, in the Select Resource dialog box, select a resource and click Select.

    If you are creating a Shared Calendar, in the Select Calendar To Copy dialog box:

    1. Choose Global or Resource calendar to use as the base for the new calendar.
    2. Click on a global or resource calendar.
    3. Click Select.
  5. On the Resource Calendars page, click the Calendar tab.
  6. On the Calendar tab, click in the Name field and enter a name for the personal or resource calendar.
  7. On the Resource Calendars page, click Save.
  8. Configure additional resource calendar settings.