Deleting Published P6 Data for Baselines Only

You can delete published baseline data. This is useful when you no longer need to report against older baselines.

To manually delete published data for baselines:

  1. On the "" Navigation Menu, expand "" Projects and click Activities or EPS.
  2. On the Activities or EPS page:
    1. On the Actions "" menu, click Define Baselines.
  3. In the Define Baselines dialog box:
    1. Select the baselines whose published data you want to delete.
    2. Click "" Context and select Delete Published Data.