Duration % of Planned
Duration % of Planned field
The actual duration percent of planned duration for an activity or all activities for the project.
The baseline duration is the activity's at complete duration from the current baseline.
Calculated as Actual Duration divided by Baseline Duration multiplied by 100. The value can exceed 100.