External Early Start
External Early Start field
The early start date for imported activities with external relationships to projects that do not exist in the database.
This field is the relationship early finish date when the lost relationship type is Finish to Start or Start to Start. When the relationship type is Start to Finish or Finish to Finish, this field is calculated as Relationship Early Finish Date minus Remaining Duration of the successor.