External Late Finish
External Late Finish field
The late finish date for imported activities with external relationships to projects that do not exist in the database.
This field is the relationship early finish date when the lost relationship type is Finish to Start or Finish to Finish. When the relationship type is Start to Start or Start to Finish, this field is calculated as Relationship Late Start plus Remaining Duration of the predecessor.