Planned Value Cost (Activities)

Planned Value Cost field

The portion of the baseline total cost of the activity that is scheduled to be completed as of the project data date.

Also known as the work scheduled to be performed for the activity. The schedule percent complete specifies how much of the activity's project baseline duration has been completed so far. Budget at completion is calculated from the baseline.

Calculated as Budget At Completion multiplied by Schedule Percent Complete.