Planned Value Cost (EPS)
Planned Value Cost field
The portion of the baseline total cost of the project that is scheduled to be completed as of the project data date. This is also known as Budgeted Cost of Work Scheduled (BCWS).
Calculated as Schedule % Complete multiplied by Budget at Completion.