Planned Value Labor Units (Activities)
Planned Value Labor Units field
The product of the budget at completion and the schedule percent complete.
The schedule percent complete specifies how much of the activity's baseline duration has been completed so far. Budget at completion is calculated from the baseline.
Calculated as Budget At Completion multiplied by Schedule Percent Complete.