Planned Value Labor Units (EPS)

Planned Value Labor Units field

The portion of baseline labor units that are scheduled to be complete as of the project data date.

The schedule percent complete specifies how much of the activity's baseline duration has been completed so far. The baseline labor units are taken from the current baseline.

Calculated as Baseline Labor Units multiplied by Schedule Percent Complete.