Schedule % Complete (Activities)
Schedule % Complete field
The activity schedule percent complete, which specifies how much of the activity's project baseline duration is complete so far.
Calculated based on where the current data date falls relative to the activity's project baseline start and finish dates.
If the data date is earlier than the baseline start, the schedule percent complete is 0. If the data date is later than the baseline finish, the schedule percent complete is 100. The schedule percent complete indicates how much of the activity duration should currently be complete, relative to the selected project baseline.