Schedule % Complete (EPS)

Schedule % Complete field

The measure of how much of the project baseline is complete so far.

Calculated as the Planned Value Cost *100 / Budget At Completion Cost.

At the EPS level, Planned Value Cost and Budget At Completion Cost are rolled-up values.