Set the Industry Type (P6 EPPM Only)
P6 Professional requires you to choose an industry type. The industry type determines the terminology and default calculation settings that display in P6 Professional. You choose an industry type from P6, Application Settings, General link.
The following table lists each industry type and its corresponding terminology and default settings. Choose the option that best matches your industry.
Industry Types
| Industry Type | Industry Terminology Examples | Default startup window in P6 Professional |
| Engineering and Construction | Budgeted Units Budgeted Cost Original Duration | Activities window |
| Government, Aerospace, and Defense | Planned Units Planned Cost Planned Duration | Projects window |
| High-Technology, Manufacturing | Planned Units Planned Cost Planned Duration | Projects window |
| Utilities, Oil, and Gas | Budgeted Units Budgeted Cost Original Duration | Projects window |