To Date: Schedule (Schedule Performance)
To Date: Schedule field
Determines project performance by calculating the variance between the baseline schedule and the actual schedule to date.
This variance helps address the basic question, "How did we do so far?" It provides concise answers such as 4 days early, No Progress, on schedule, or 12 days late.
This value is expressed in units of time accompanied by a convenient visual indicator mapped to performance thresholds you can define. The value can be derived based on costs or labor units and will often yield different results.
Calculated as (Baseline Duration multiplied by Performance % Complete) minus (Baseline Duration multiplied by Schedule % Complete). Where Performance % Complete equals Earned Value divided by Budget at Completion and Schedule % Complete equals Planned Value divided by Budget at Completion.