To Date: Schedule (Earned Value)
To Date: Schedule field
Determines project performance by calculating the variance between actual and scheduled labor units or cost.
This variance helps address the basic question, "How did we do so far?" It provides concise answers such as 4 days early, No Progress, on schedule, or 12 days late.
For costs, calculated as Earned Value Cost minus Planned Value Cost.
For labor units, calculated as Earned Value Labor Units minus Planned Value Labor Units.