Variance - Total Cost
Variance - Total Cost field
The difference between the project baseline total cost and at completion total cost.
Calculated as BL Total Cost minus At Completion Total Cost.
Variance - Total Cost field
The difference between the project baseline total cost and at completion total cost.
Calculated as BL Total Cost minus At Completion Total Cost.