Variance At Completion
Variance At Completion field
The difference between the baseline total cost and the current estimate of total cost. A negative value indicates an estimated cost overrun.
Budget At Completion is calculated from the current baseline.
Calculated as Budget At Completion minus Estimate At Completion.