Variance BL1 - Total Cost

Variance BL1 - Total Cost field

The difference between the primary baseline total cost and the at completion total cost. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as BL1 Total Cost minus At Completion Total Cost.