Variance BL1 - Start Date

Variance BL1 - Start Date field

The duration between the current project start date and the primary baseline start date. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.

Calculated as Start minus BL1 Start.