Variance BL Project - Duration
Variance BL Project - Duration field
The duration between the activity's baseline duration and the at completion duration. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.
Calculated as Planned Duration minus At Completion Duration.